Hyonix - Adding new carrier in London – Maintenance details

All systems operational

Adding new carrier in London

Completed
Scheduled for November 30, 2024 at 2:00 PM – 6:07 PM

Affects

Core Networks
London, UK (LON1)
Updates
  • Completed
    November 30, 2024 at 6:07 PM
    Completed
    November 30, 2024 at 6:07 PM

    Maintenance has been completed! Network has been normalized. We do not expect any further interruptions at this time.

    Our team has successfully added another 2x 100Gbps network uplink with more direct connections toward major networks at this time.

    We are looking to perform even more upgrades in the next 2 weeks. Rest assured that upgrades will only be done in weekend to prevent disruptions to customers usage.

    If you still experience any issues in London, please reach out to us via ticket.

    Thank you for your patience and understanding!

  • In progress
    November 30, 2024 at 2:02 PM
    In progress
    November 30, 2024 at 2:02 PM

    Maintenance is now in progress.

  • Planned
    November 30, 2024 at 2:00 PM
    Planned
    November 30, 2024 at 2:00 PM

    We are adding new network PoP and bringing in new upstreams that would provide more redundancy and enhance performance further!

    Some minor network disturbance is expected at this time as we shift network loads to the new upstream once online!